Planning / Projects & stages
A project groups work towards an outcome. Its stages describe the pieces of work, estimated working duration and resources needed to get there.
Understand the model ↓See the worked example →A project brings together stages, a priority, an optional target and a hard deadline. A stage has its own details, status, Estimated Duration and assigned resources. External waiting can use a release date without consuming productive staff time.
Estimated Duration sizes the planned work in working minutes. Remaining is calculated from scheduled intervals relative to the planning clock; it is not a separate editable estimate. A two-hour stage may span a break or continue tomorrow.
Sequence orders eligible stages, but does not create a prerequisite. Add an explicit dependency when a review really must wait for a build.
Project completion follows the latest required stage finish. An unfinished stage with no feasible forecast leaves project completion unknown; Can You Just does not invent a date just to fill a column.
Archive projects to remove them from future planning while retaining history. Archive is not the same as marking unfinished work complete.
A FICTIONAL SCHEDULING STORY
Alice prepares the work from 09:00 to 11:00. Ben reviews it from 11:00 to noon.
Alice takes a committed one-hour export fix at 10:00. Ben’s calendar, estimate and assignment stay unchanged.
Project completion: Mon 12:00
Project completion: Mon 13:00
Example assumptions. Monday 19 October 2026. Both people work 09:00–18:00 without breaks in this isolated example. One explicit stage dependency connects preparation to review.
THE CONSEQUENCE
Preparation finishes at noon. The finish-to-start dependency prevents Ben reviewing it at 11:00.
THE REVISED PLAN
Ben reviews from 12:00 to 13:00. His work moved because its prerequisite moved, not because someone edited his task.